Quick answer

Do I need planning permission for commercial solar in Wales?

Usually not for a roof. Part 43 of Schedule 2 to the Welsh General Permitted Development Order gives permitted development for solar PV on any building that is not a house or block of flats, if the panels project no more than 20 cm from a wall or pitched roof, no more than 1 m above a flat roof, and sit at least 1 m inside the roof edge. Listed-building curtilages and scheduled monuments are excluded. Grid connection (G99) is a separate approval from your network operator.

Wales is part of the same electricity market and the same tax system as England, so the economics of a rooftop array follow the same pattern: generate during working hours, use it on site, and export only the surplus. What changes at the border is the law. Planning is devolved, large generating projects are decided by Welsh Ministers rather than Whitehall, and the grid is split between two operators with different coverage. This page sets out those differences for a business owner or facilities manager. If you are comparing Wales with other nations, the equivalent guide for Scotland covers Class 6J and the Scottish operators, and our compliance guide covers the English rules.

Planning: Part 43 permitted development in Wales

The Welsh right was inserted into the Town and Country Planning (General Permitted Development) Order 1995 as Part 43 by Welsh Statutory Instrument 2012/2318. It has two classes that matter to a business: Class A for equipment fixed to a building, and Class B for a freestanding array in the grounds.

Class A: panels on a commercial roof or wall

Class A permits the installation, alteration or replacement of solar PV or solar thermal equipment on a building other than a dwellinghouse or block of flats. That covers factories, warehouses, offices, farm buildings, retail units and similar. The development is not permitted if:

  • on a wall or pitched roof, the equipment would protrude more than 20 centimetres beyond the plane of the wall or roof slope;
  • on a flat roof, it would protrude more than 1 metre above the plane of the roof;
  • on a roof, it would sit within 1 metre of the external edge of that roof;
  • on a wall, it would be within 1 metre of a junction with another wall or the roof;
  • the building is on article 1(5) land or in a World Heritage Site and the panels would sit on a wall or roof slope that fronts a highway;
  • the building is within the curtilage of a listed building, or the site is a scheduled monument.

Two conditions apply to every installation: the equipment must, so far as practicable, be sited to minimise its effect on the building's appearance and on the amenity of the area, and it must be removed as soon as reasonably practicable once it is no longer needed for microgeneration. A Welsh Government written answer (WQ90508, January 2024) confirms there is no cap on the number of panels on a non-domestic roof, provided these criteria are met.

The practical consequence is that the 1 m edge setback, not the building's size, is what limits a Welsh roof array. On a large warehouse that costs very little usable area; on a narrow workshop or a small pitched unit it can remove a meaningful share of the roof. Ask your installer to show the setback on the layout drawing before you compare quotes on kWp.

Class B: a freestanding array in the grounds

Class B is far tighter and is the reason most Welsh ground-mount schemes need a planning application. A stand-alone array is not permitted development if there would be more than one in the curtilage, if any part exceeds 4 metres in height, if it sits within 5 metres of the curtilage boundary, or if the panels have a surface area over 9 square metres (or any dimension over 3 metres). It is also excluded in the curtilage of a listed building or on a scheduled monument. Nine square metres is a few panels, so for any real commercial output the freestanding route means a full application to the local planning authority. See our ground-mounted solar guide for what that application needs, and check the current consolidated order on legislation.gov.uk before submitting, because the 2012 text may have been amended since.

Large schemes: Developments of National Significance

Wales has its own consenting route for big generation. Under the Planning (Wales) Act 2015, onshore generating stations from 10 MW up to 350 MW, solar included, were decided by Welsh Ministers as Developments of National Significance, with the UK Secretary of State handling anything larger. The Infrastructure (Wales) Act 2024 is replacing that regime with Infrastructure Consent for significant infrastructure projects, with a band of 50 to 350 MW for non-wind generating stations. A rooftop system of a few hundred kilowatts is nowhere near these thresholds, but a business planning a large on-site solar farm for a campus or industrial estate should confirm which regime applies at the time of application. Source: Senedd Research.

Grid connection: NGED in the south, SP Manweb in the north

Any generator over the G98 limit needs a G99 application to the local distribution network operator before it can be connected. Wales is covered by two operators, so the first question for any site is which one owns the network at the postcode:

AreaOperatorTypical postcodes
South Wales, including Cardiff, Newport, Swansea and BarryNational Grid Electricity Distribution (NGED)CF, NP, SA, parts of LD
North Wales, including Wrexham, Deeside and LlandudnoSP Energy Networks (SP Manweb)LL, CH and parts of SY

Confirm the operator for your exact address using the operator's own postcode lookup, since boundaries do not follow county lines. The G99 process, the timelines to expect and the zero-export option for constrained networks are explained in our DNO grid connection guide, and the current delays are covered in grid connection delays in 2026. For a city-specific view see Cardiff and Barry.

Tax relief and funding for Welsh businesses

Capital allowances are set by HMRC and apply across the UK, so a Welsh company claims exactly as an English one. Solar PV qualifies as plant and machinery, and the Annual Investment Allowance lets a business deduct qualifying spend up to its annual limit from profits in the year of purchase. Solar PV is treated as special-rate expenditure, so full expensing does not apply and the Annual Investment Allowance is the route. We explain the claim and the limits in solar capital allowances and the Annual Investment Allowance guide.

Grant availability is where Wales can differ, and it changes often. Funding programmes open and close, and several have been paused to new solar applications, so treat any figure on a third-party page as out of date until you have checked it with the scheme owner. Our commercial solar grants page keeps the UK-wide picture, and finance options covers loans, leasing and power purchase agreements, which do not depend on grant funding. The Welsh Government has set a target of meeting all Welsh electricity demand from renewables by 2035, which is the policy background for local support, but a target is not a funded scheme for your project.

Which Welsh roofs work best

The same engineering logic applies everywhere: a large, unshaded, structurally sound roof with a daytime electricity load pays back fastest. In Wales that typically means logistics and manufacturing units on the south Wales corridor, food processing and agricultural buildings in the borders and mid Wales, and large retail and leisure sites along the north Wales coast. Before you request quotes, have three things ready: twelve months of half-hourly meter data, the roof age and construction (asbestos cement sheeting changes the method, see asbestos roof options), and your site's maximum import capacity. Our roof assessment guide and cost guide show how those inputs drive system size and price.

Wales sits next to several English counties whose operators and rules differ, so if your business spans the border the pages for Gloucestershire, Herefordshire, Shropshire and Cheshire apply to the English sites.

What to do next

  1. Check whether the roof falls inside the Part 43 limits, including the 1 m edge setback and any listed-building curtilage.
  2. Identify your network operator (NGED or SP Manweb) and ask about available export capacity.
  3. Gather your meter data and roof details.
  4. Send your site details and compare them on kWp after setbacks, not headline size.

We are an independent publisher, not an installer. Use the form below and we reply by email.

Frequently Asked Questions

Do I need planning permission for a commercial solar roof in Wales?

Usually not. Part 43 Class A of the Welsh General Permitted Development Order permits solar PV on buildings other than dwellinghouses and blocks of flats, provided panels project no more than 20 cm from a wall or pitched roof, no more than 1 m above a flat roof, and sit at least 1 m inside the roof edge. Listed-building curtilages and scheduled monuments are excluded.

Is there a limit on the number of panels on a Welsh commercial roof?

No. A Welsh Government written answer in January 2024 (WQ90508) confirmed there is no cap on the number of panels on a non-domestic roof, provided the Class A criteria are met.

Can I put a ground-mounted solar array on my Welsh business premises without planning permission?

Only a very small one. Class B limits a stand-alone array to one per curtilage, 4 m in height, 5 m from the boundary and 9 square metres of panel surface. Anything larger needs a planning application to the local authority.

Who handles the grid connection in Wales?

National Grid Electricity Distribution (NGED) covers south Wales and SP Energy Networks (SP Manweb) covers north Wales. Systems above the G98 limit need a G99 application to the operator that owns the network at your site.

Who decides very large solar schemes in Wales?

Under the Planning (Wales) Act 2015, onshore generating stations from 10 MW to 350 MW were Developments of National Significance decided by Welsh Ministers. The Infrastructure (Wales) Act 2024 is replacing that with Infrastructure Consent, with a 50 to 350 MW band for non-wind generation. Confirm the current regime before applying.

Is tax relief different in Wales?

No. Capital allowances, including the Annual Investment Allowance, are set by HMRC and apply to Welsh businesses in the same way as English ones.

Ready to Reduce Your Energy Costs?

Send your site details and we reply by email. We are an independent publisher — we reply by email, and this is not a sales call.

Independent publisher · We reply by email · No obligation

Check any installer against these registers — we publish this site, we are not an installer