Installing Commercial Solar Panels: A Site Manager's Checklist
What to prepare, watch and collect when a solar crew works on your site, from the occupier's side of the fence.
Quick answer
What should a site manager prepare for installing commercial solar panels?
Four things: a safe, agreed access and working-at-height plan; a planned electrical shutdown for the AC tie-in; the asbestos register and any roof constraints shared with the contractor; and a commissioning and handover list so the system is tested, documented and connected properly. The checklist below is written from the occupier's side of the fence, not the installer's.
Most guides to installing commercial solar panels describe the project from the installer's point of view: survey, design, connection application, build. This one is for the person who has to keep a site running while the crew is on the roof. It covers what to have ready before the contractor arrives, what to watch during the install, and what you should hold in your hands at the end. It sits alongside our commercial solar installation process page, which sets out the stages in the order they happen; use that for the project plan and this for the practical running of the site.
Before anyone arrives
- Confirm the grid position. Systems above the G98 limit need a G99 application and approval from the network operator before they are connected. Ask for the approval reference and any conditions, such as export limits. Our DNO grid connection guide explains the process, and the grid delays page covers why timelines can slip.
- Share the asbestos register and roof condition. The contractor must know before they plan access. If the roof is fibre cement or fragile, read our guide to solar on metal and fibre-cement roofs first.
- Agree the structural sign-off. The design pack should include the engineer's confirmation that the roof can carry the array. File it.
- Tell your insurer and landlord if either needs to know, and keep the consents with the project file.
- Check planning. Most non-domestic rooftop arrays in England are permitted development within limits, but listed buildings and protected areas need checking. See the compliance guide.
Health and safety: who is responsible for what
A solar install is construction work, so the Construction (Design and Management) Regulations 2015 apply. As the client you hold duties under CDM 2015, including making suitable arrangements for managing the project and providing the contractor with the pre-construction information they need, such as asbestos details and site hazards. Where more than one contractor is involved, a principal designer and principal contractor must be appointed. Ask your installer to confirm how they are meeting these duties and to give you their risk assessments and method statements (RAMS) before they start.
Work on roofs falls under the Work at Height Regulations 2005. The hierarchy is to avoid work at height where possible, prevent falls using collective protection such as edge protection or scaffold, and only then use personal protective measures. Ask to see how the contractor will protect the roof edge, how they will keep people off fragile areas, and how they will stop tools and materials falling onto the ground below. Plan the ground too: designate a laydown area, keep pedestrians and vehicles out of the drop zone, and agree delivery slots so lorries do not block your operation.
Access, lifting and disruption
Think about the practical footprint of the job:
- Roof access: permanent ladders, hatches, scaffold or a mobile elevated platform, and where each can stand.
- Lifting: pallets of modules usually go up by telehandler, crane or hoist. Agree who arranges it, the ground conditions and any road or pavement closures.
- Parking and welfare: where the crew park, where welfare facilities sit, and whether they need access to your toilets.
- Noise and working hours: particularly near offices, care settings or residential neighbours.
- Security: site induction, passes and whether materials can be stored overnight.
The electrical tie-in: plan the shutdown
The array can be assembled on the roof with little effect on your operation, but connecting it to your electrical system normally needs a planned outage on the supply to the switchgear involved. Agree the date, duration and what stops during it, and warn anyone who depends on the supply: refrigeration, servers, process lines, security systems, fire alarms. Ask the installer how isolation and proving dead will be done and who holds the permit. Two practical points are easy to miss. First, the DC side of a solar array is live whenever there is daylight, which is why only competent electricians should handle it. Second, your site's other contractors should be told about the new isolation points and labelling so that future maintenance does not catch anyone out.
Commissioning and tests
A finished array is not a working system until it has been tested and, where required, accepted by the network operator. Expect the installer to carry out and record inspection and testing of the installation to BS 7671, the wiring regulations, and commissioning tests on the PV system under IEC 62446-1, which covers documentation, inspection and testing for grid-connected systems. Where the network operator requires witnessing or specific commissioning evidence under the G99 approval, the installer should arrange it and confirm the date with you. Ask to be present for the key tests: insulation resistance, polarity, string voltage and the protection settings. The system should be energised only when the connection approval and test records are in place.
What you should receive at handover
- As-built drawings, string layout and single-line diagram.
- Electrical installation certificate and PV commissioning test records.
- The network operator's G99 approval or commissioning confirmation.
- Datasheets, installation and operation manuals for modules, inverters and mounting system.
- Warranty documents with serial numbers: modules, inverters, mounting and workmanship.
- Monitoring login and an explanation of the alarms; see our monitoring guide.
- Maintenance schedule and emergency isolation instructions; see commercial solar panel maintenance.
- The roof weatherproofing warranty for penetrations, if any, and the structural sign-off.
- Invoices and an itemised list of assets for your tax claim; see solar capital allowances.
Ask for the pack in draft before final payment. It is far easier to get missing certificates while the crew is still engaged than months later.
After the crew leaves
Check that the roof has been left clean and that any damaged flashings, lights or cables have been made good. Walk the system with the installer, locate the isolators and make sure your own facilities team can find them. Put the monitoring alerts into a mailbox that someone reads. Diary the first inspection and the date the warranty periods end. If you plan to claim tax relief, keep the invoices with the date the system was brought into use, as that affects when the claim falls.
Questions to ask your installer before you sign
- Who is the principal contractor, and can I see the RAMS and CDM arrangements?
- What shutdown do you need, how long will it last and who authorises it?
- Who arranges the structural check, the asbestos survey and any licensed work?
- What is the G99 position, and what happens if the network operator reduces my export limit?
- What tests will you carry out, and can I attend them?
- What does the handover pack contain, and when will I receive it?
If you do not yet have installers lined up, send your site details and send them this list with your site details. We are an independent publisher, not an installer, so we reply by email. Our roof assessment guide will help you decide what to share first.
Frequently Asked Questions
How long does a commercial solar installation take on site?
It depends on system size, roof access and the connection date, so there is no single answer. Ask the installer for a programme that separates the roof work, the electrical tie-in and commissioning, and remember that commissioning can depend on the network operator's approval, not just the crew.
Does installing commercial solar panels require a power shutdown?
Normally yes, for the AC connection into your switchgear. The roof work can usually run without stopping the business, but the tie-in needs a planned outage that you should agree in advance, including what stops and for how long.
Do CDM regulations apply to a commercial solar installation?
Yes. A solar install is construction work, so the Construction (Design and Management) Regulations 2015 apply and the client has duties, including providing pre-construction information such as asbestos details. Ask your installer how they are meeting the principal contractor and principal designer requirements.
What tests are done when a commercial solar system is commissioned?
The installer should inspect and test the installation to BS 7671 and carry out PV commissioning tests under IEC 62446-1, and arrange any witnessing the network operator requires under the G99 approval. Ask for the test records in the handover pack.
What documents should I get at handover?
As-built drawings, electrical and commissioning certificates, the G99 approval, manuals and datasheets, warranty documents with serial numbers, monitoring access, a maintenance schedule and the structural and roof warranty paperwork.